Project Updates


THE CATALYST: STAGE ONE

  • Developer - DeMol Group of Companies

  • Architect - MJA Studio

  • Builder - Kastle

  • Contact - steve@tdgc.com.au


View fullsize
Mixed Use - Retail - Commercial - 70 Apartments

Mixed Use - Retail - Commercial - 70 Apartments

Project Updates

  • Expected construction completion - mid 2020

  • Construction on site continues to progress steadily with level eight roofing due for completion by the end of the month.

  • Fit-out will progress in early 2020.

(last edit: December 2019)


PUBLIC OPEN SPACE: STAGE ONE

  • Developer - City of Swan

  • Construction Award - Environmental Industries

  • Contact - heartofmidland@swan.wa.gov.au


Kick-about - Youth hangout - Historic interpretation wall

Kick-about - Youth hangout - Historic interpretation wall

Project Updates:

  • Expected construction completion - mid 2020

  • Works under Contract completed so far includes site mobilisation and establishment, installation of sub soil drainage and majority of the electrical groundworks.

  • The City received grant funding from Lotterywest and on 7th of November 2019, the grant certificate presentation was held on site with Hon Simone McGurk MLA.

(last edit: December 2019)


CIVIL WORKS UPDATES

Developer - City of Swan

Civil Contractor - Tracc Civil

Streetscape Contractor - Environmental Industries

Contact - heartofmidland@swan.wa.gov.au


View fullsize
Construction and widening of The Avenue, Midland

Construction and widening of The Avenue, Midland

Project Updates:

  • The construction of The Avenue is split into 2 stages

  • Stage 2 Civil works is now well advanced with drainage, road base and kerbing now in place. Due for completion in early 2020.  

  • Stage 1 construction will commence early in 2020 and will take approximately 14 weeks to complete.

  • Further information about road closures are available at the City of Swan website.

(last edit: December 2019)